Australia & New Zealand

Project
CG2 Installation
Client
ANSTO
Location
Australia
Overview
The CG2 installation was an essential high-risk manoeuvre carried out within a nuclear environment at the ANSTO facility. The manoeuvre involved the removal and storage of an old shutter and in-pile plug and the installation of a new in-pile plug-guide assembly and shutter. blueVisions managed the preparation of a very descriptive and detailed manual to carry out the manoeuvre and then worked closely with the engineers to develop an integrated schedule for the six-week execution phase. blueVisions maintained a high level of quality assurance during the execution phase from the CG2 Control Room, which was located within close vicinity of the manoeuvre. This involved extensive management and administrative support including the development and implementation of templates, facilitating meetings and lessons learnt between the day and night shift and tracking the status of the works. The accurate recording of information ensured a seamless transition between the two teams and the successful installation of CG2 within a high-risk environment.

Project
Risk Management Framework
Client
TransGrid
Location
Australia
Overview
Blue Visions Management Pty Ltd together with the Institute of Management were engaged by TranGrid to improve the network provider’s management of risk. With a project environment comprising more than 50 project managers with an average of 100 projects running per year across TransGrid’s portfolio, blueVisions developed a Risk Management framework and Guidelines, including tools to support the new framework and training for TransGrid staff. As a result, TransGrid have maintained effective visibility and control over risks in a consistent manner, clear and consistent processes for risk assessment, demonstrated effective overall management of risk and an increase in competency in project/program managers in risk management achieved through training, coaching and support.

Project
Newcastle University Residential Low Voltage Consolidation
Client
University of Newcastle
Location
Newcastle, NSW Australia
Overview
The Newcastle University Residential Low Voltage Consolidation project encompassed the rationalising of low voltage supplies from the network to twelve separate buildings to be fed from one central supply point. blueVisions’ programming and planning ensured the required works to be staged to provide the client with greater control in the delivery of each phase along with rigid timeframes to mitigate the risk of cost blow out in relation to back up power generation.

Project
Belmore Park Zone Substation
Client
Energy Australia
Location
Australia
Overview
The Project involves the construction of the Belmore Park Zone Substation between Campbell Street, Pitt Street and Hay Street. The substation building consists of three basement levels, ground floor plus five floors. The zone substation is equipped with five transformers and a multi-section busbar enabling 132kV interconnection between the Haymarket Bulk Supply Point (BSP), the City South and Rose Bay zone substations and the Riley Street subtransmission switching station (STSS). The 132kV cables would be installed in the existing City South Cable Tunnel (CSCT), which runs directly beneath Campbell Street at a depth of 19 meters. A shaft and stub tunnel connection from Belmore Park Zone Substation would facilitate access to the CSCT to enable up to eight new feeders to be connected at the substation. The zone substation would act as a central point for the 11kV distribution network in the southern Sydney CBD.

Project
Solomon 1 Power Plant
Client
Fortecue Metal Group
Location
Australia
Overview
Solomon Hub is an open-cut ore mine, 60 km north of Tom Price in Western Australia, fully owned by Fortescue Metal Group (FMG). The project included Engineering, Procurement, Construction and Commissioning of the turbines and all Balance of Plant (earthworks, various housing buildings, piping, cabling, tanks, foundations, roads, pipe bridges etc). Bluevisions was responsible for preparation of Tender programme for the EPC Solomon I Power Station project at Pilbara, for United Group ltd (UGL) consisting of six Wartsila reciprocating engines and two GE LM 6000 engines plus all Balance of Plant (BOP) works for this dual fuel power station.

Project
Waddamana Lindisfarne 200kv Transmission line
Client
John Holland
Location
TAS, Australia
Overview
Project entailed the construction of 200 km new transmission line over rugged terrain in the north of Tasmania. blueVisions was commissioned to provide specialised planning services which was successfully achieved and approved by the client.

Project
Zone Substations
Client
Ausgrid
Location
Sydney, NSW Australia
Overview
Ausgrid had undertaken a massive capital program of upgrading the power capacity servicing Sydney which included developing a ring of zone substations circling the Sydney CBD, a new tunnel system which transmits the high voltage cables to the new zone substations. blueVisions’ responsibility was commissioned to provide specialised planning services for many of these zone substations over 7 years. Design review and site inspections were also under our responsibility.

Project
Beaconsfield West Transmission Zone Substation
Client
Brookfield
Location
NSW, Australia
Overview
Project involved demolition of the existing building and redevelopment of Beaconsfield West 330/132kv Substation from its existing arrangement to a larger and higher capacity substation. blueVisions undertook a review of the design, attended site for the site inspections, assisted Brookfield in preparing a detailed design and construction programme for their tender submission.

Project
Power Supply Upgrade Program
Client
Transport for NSW
Location
NSW, Australia
Overview
The Power Supply Upgrade Program is designed to ensure Sydney’s rail network is able to meet expected power requirements to support future timetables and new generations of air-conditioned fleet (e.g. the Waratah trains). The program involves the construction of new electrical infrastructure and upgrades to substations, section huts, overhead wiring and feeders across the network. The program includes Traction Supply Upgrade (TSU) Waratah Program, Central Station Power Upgrade, Signal Power Supply Upgrade, North Eveleigh 11kV Relocation. The benefits of Power Supply Upgrade Program will support the introduction of air-conditioned trains into service, provide additional power to operate trains on the network, improve service reliability by reducing the risk of disruption to rail services.
Asia

Project
Power Plants in Indonesia
Client
PT PLN (Persero)
Location
Java, Indonesia
Overview
Partnering with ReConsult, blueVisions was appointed to build an Integrated Project Management to assist Indonesia’s national power supply company, PT PLN (Persero), to build a total of 35000 MW power plants by 2019. The 35,000 MW program aims to meet the electricity needs of Indonesians from Sabang to Merauke, which are the west and the east ends of the Indonesian archipelago. This will bring a significant impact on the economic growth outside Java, which previously lacked power supplies. Over the next five years, the government together with PLN and the private sector will build 109 plants. blueVisions brings Project Controls experts from different countries with background and specialties in managing power generation projects to assist the client in ensuring that they meet their requirements and deadlines.